Free Master Schedule Builder

Generate bid-ready Gantt schedules in 3 minutes.

1General Project Information

2Smart Context & Site Constraints

Work Hours

Site Logistics

Compliance & Supply Chain

3Master Construction Milestones

Timeline units

Add a project start date in step 1 to see real dates and get alerts when tasks fall behind.

Progress0%
Link:
Progress0%
Link:
Progress0%
Link:
Progress0%
Link:
Progress0%
Link:
Progress0%
Link:
Progress0%
2 wks

Live preview · 8.5 × 11

Prime Bid · Master Schedule

Project Name

Owner / Developer: Client Name

Your Company

Base Bid

$0

Total Duration

64.3 wks

Contingency

2 wks

Master Timeline

WK0WK12WK24WK36WK48WK60
Pre-Construction & Municipal PermittingEstimator
8.7 wks
Site Mobilization & EarthworksSuperintendent
4 wks
Substructure & Foundation
8 wks
Superstructure & Building Envelope
17.3 wks
Interior MEP Rough-Ins & Drywall
17.3 wks
Sub-Trade Commissioning & Inspections
4 wks
Substantial Completion & Handover
3 wks
Contingency float
Critical path (float 0)Scheduled▼ Sub-trade mobilization

Milestone, Resource & Critical Path Matrix

#PhaseDurationWindowLinkFloatStatus
1Pre-Construction & Municipal PermittingEstimatorTrade buyout; long-lead releases.8.7 wksW1–W9Start—Critical
2Site Mobilization & EarthworksSuperintendentExcavation & servicing subs mobilize.4 wksW9–W13FS—Critical
3Substructure & FoundationFormwork, rebar, concrete trades on site.8 wksW13–W21FS—Critical
4Superstructure & Building EnvelopeSteel, roofing, glazing, cladding.17.3 wksW21–W38FS—Critical
5Interior MEP Rough-Ins & DrywallMEP subs mobilize; drywall follows.17.3 wksW39–W56FS—Critical
6Sub-Trade Commissioning & InspectionsTAB, fire alarm verification, AHJ inspections.4 wksW56–W60FS—Critical
7Substantial Completion & HandoverDeficiencies, closeout docs, training.3 wksW60–W63FS—Critical

Critical path: Pre-Construction & Municipal Permitting → Site Mobilization & Earthworks → Substructure & Foundation → Superstructure & Building Envelope → Interior MEP Rough-Ins & Drywall → Sub-Trade Commissioning & Inspections → Substantial Completion & Handover

Schedule Assumptions

No site constraints selected.

Durations are estimates subject to award date, permits and site conditions.

Need the full proposal? Generate it with CrewHQ AI — thecrewhq.ca

Full proposal sections are available in CrewHQ

Generate the full proposal with AI